Back to the classroom: Gateley Built Environment restores Badgerbrook Primary School
Our team has delivered an insurance reinstatement project for Badgerbrook Primary School in Leicestershire, part of the Discovery Trust, after a devastating flash flood left pupils and staff unable to return to their classrooms.
The whole ground floor of the primary school, including ten classrooms, a kitchen and a hall, was flooded after the nearby Whetstone Brook burst its banks. The flooding ruined low-level building fabric including flooring, timberwork and decoration, as well as damaging equipment, such as books, wooden furniture, toys and laptops. As a result, the school was forced to arrange temporary classrooms on external playground areas, while also providing alternative tuition options. This included organising bus transport to other sites across the county for some pupils, alongside online learning.
Mike Boast and David Abell, from our Nottingham and Glaston offices, were appointed to deliver building consultancy and civil engineering expertise as part of full project-managed services, working in partnership with the school and trust leadership teams. This included specifying the reinstatement requirements, designing the programme of works, and coordinating and managing contractors during the initial strip-out and drying process, as well as throughout the complete reinstatement of the ground floor.
Passing the test under time pressure
This was a challenging project, with time being of the utmost importance, alongside minimising further disruption to the school and delivering the works cost-effectively for the insurer.
Additionally, with the school accommodating approximately 400 pupils, there were significant costs involved with relocating lessons to other facilities while the works were ongoing. So, temporary classrooms were set up to ensure that certain lessons could remain on site where possible, limiting disruption and reducing additional expenses.
The project was managed on a negotiated tender basis, with the local authority-approved contractor having already completed building works at the school previously. This familiarity was extremely beneficial in speeding up the programme of works while still maintaining high levels of build quality and meeting regulatory requirements.
In order to keep the school operating as much as possible, the reinstatement works were coordinated using a phased approach, allowing access to and use of certain facilities including the kitchen, canteen and first-floor classrooms for early years pupils. Then, following deep cleaning and sanitisation works to comply with health and safety guidance, the kitchen repair works were completed during the summer holidays to limit interruptions to school operations.
An A grade result
Despite the large-scale nature of the incident, the project team involved adopted a carefully planned and strategically managed approach that enabled the majority of the school to reopen less than three months after the flooding occurred, several months ahead of schedule.
Nathan Odom, director of estates and place planning at Discovery Trust, said: “Mike Boast and Gateley Built Environment have become a valued partner to Discovery Trust, particularly in supporting us following the flooding at Badgerbrook Primary School. Their responsive, practical and collaborative approach helped us navigate a challenging situation and supported us in getting the school back up and running.”
Mike Boast, commercial director at Gateley Built Environment, commented: “It was a real pleasure to support Discovery Trust with the reinstatement of Badgerbrook Primary School. Leading projects at the heart of local communities is always rewarding, and this one was certainly no exception. Thanks to the hard work and dedication of everyone involved, we were able to return pupils to their classrooms in record time so they could begin the new term and enjoy their newly refurbished facilities. Following the completion of the works, we are proud to continue working with the school on flood remediation and prevention measures to help prevent incidents like this from happening again.”